Building Control Application details for 2015/0720/BR
- Building Regs No.
- 2015/0720/BR
- Application Type
- Building Regulations-Full Plan
- Planning Ref
- 2014/00956/FUL
- Decision
- Approved Conditionally
- Location
- Rear of Tesco Store, Mariners Way, Rhoose
- Commencement Date
- 15/07/2015
- Decision Date
- 15/07/2015
- Completion Date
- -
- Valid Date
- 03/07/2015
- Proposal
- Development of 2 houses and 6 flats
- Decision
- Approved Conditionally
- Decision Date
- 15/07/2015
Code | Condition Details |
---|---|
ns | Welsh Water should be consulte and a section 104 agreement obtained for the site connection to the public sewer system. |
ns | Provide a Target Carbon Dioxide Emission Rate (TER) for the proposed dwelling. |
ns | on completion an Air Permeability test is to be carried out on each type of dwelling on the site. The results of this test are to be submitted to the Building Control Section prior to the issuing of the completion certificate. |
ns | Provide an energy performance certificate for each dwelling. |
ns | Structural calculations & details are required to be deposited for the retaining walls. |
ns | Provide the manufacturers details and span tables for the reinforced concrete floor beams. |
ns | The proposal has been identified as being in area which may be affected by Radon. Once the work has been completed it is advisablethat the property is tested in accordance with National Radiological Protection Board's recommendations. Any cracks in the floor slab, walls, or service entries are to be suitably sealed with flexible sealers. A radon tray is to be provided at GF dpc level. |
ns | Provide pre-completion sound test certificates for each unit. |
ns | Provide manufacturers calculations and details for the proposed roof trusses. Indicate the bracing to be provided to the roof trusses. |
ns | Provide manufacturers details of the WOLF floor system. |
ns | Provide a door schedule for the proposed flats. |
ns | Supply a section plan through the stairway showing the pitch, risers, goings headroom and heights of handrails for the proposed flats. |
ns | Provide smoke detectors in the hallway of each flat. |
ns | Provide interlinked smoke detectors to the FF landing area of each house. |
ns | Provide the full manufacturers details and span tables for the lintels. |
File name | Created date | |
---|---|---|
Building Control Documents | ||
Comp Certs for Flats 1 - 6 | 13/06/2016 | |
Comp Cert House 1 & House 2 | 07/04/2016 |