A01 |
The development shall begin no later than five years from the date of this decision.
Reason:
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990.
|
A02 |
The development shall be carried out in accordance with the following approved plans and documents:
01 Location Plan (received 5th April 2022)
03 Rev I Proposed Block Plan (received 10th March 2023)
12 Outbuilding Conversions- Proposed Plans and Elevations (received 5th April 2022)
Cadair Idr... |
OCC03 |
The development shall be occupied as holiday accommodation only and shall not be occupied as a person’s sole or main place of residence or by any other persons. An up to date register shall be kept at the holiday accommodation hereby permitted and be made available for inspection by the Local Planni... |
NSA |
No touring caravans or camper vans are permitted to pitch at the site at any time.
Reason:
To minimise conflict between highway users in accordance with Policy MD2 (Design of New Development) of the Local Development Plan.
|
NS |
In the event following first beneficial use that the site is not used for the tourism accommodation hereby approved for a continuous twelve month period, this use shall permanently cease and all glamping pods, and grass protection matting along with the crushed stone filling shall be removed within ... |
NSA |
No development shall commence on site until a detailed scheme for the surface water drainage of the whole site, demonstrating how flows from the wider catchment will be dealt with in the design proposals, have been submitted and approved in writing by the Local Planning Authority. The works shall be... |
LS08 |
All the trees and hedges to be retained and/or any trees whose canopies overhang the site shall be protected by strong fencing, the location and type to be first submitted to approved in writing by the Local Planning Authority. The fencing shall be erected in accordance with the approved details bef... |
A04 |
Notwithstanding the submitted details, prior to the commencement of the works on the conversion of the buildings hereby approved, a schedule of finishing materials to be used, including for the walls, roofs, windows, roof lights and doors shall be submitted to and approved in writing by the Local Pl... |
NSA |
Prior to the commencement of works to layout access and parking to the converted buildings and larger glamping pods hereby approved, details of surfacing materials shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with t... |
NSA |
Prior to the first time that it is installed, details of the temporary toilet and shower block, including the time period within the year that it will be present on the site, shall be submitted to and approved in writing by the Local Planning Authority. The temporary toilet and shower block shall be... |
NSA |
Prior to the construction of the camping area within Zone 3 as shown drawing no. Plan 03 Rev I Block Plan, a reptile and amphibian barrier shall be erected around the area of development within Zone 3 in accordance with a plan and method statement that shall have been first submitted to and approved... |
NSA |
Prior to the first beneficial use of the development hereby approved, an ecological mitigation, enhancement and management plan for the site shall be submitted to and approved in writing by the Local Planning Authority. The plan shall cover a period of 10 years from the first beneficial use of the s... |
NSA |
Prior to the first beneficial use of the development hereby approved, a lighting plan shall be submitted to and approved in writing by the Local Planning Authority. The plan shall be implemented and lighting shall be maintained in accordance with the approved details, for as long as it exist.
Rea... |
NSA |
Prior to the first beneficial use of the development hereby approved, bat boxes and bird nesting boxes/features shall be provided in accordance with details that shall be first submitted to and approved in writing by the Local Planning Authority.
Reason:
In the interests of biodiversity, and ... |
NSA |
Prior to the first beneficial use of each unit of accommodation, arrangements for the provision of cycle parking/storage for that unit of accommodation shall be submitted to and approved in writing by the Local Planning Authority. The cycle parking shall be provided in accordance with the submitted ... |
NSA |
Prior to the first beneficial use of the development hereby approved, details of the cycle hire scheme, the cycle storage area for this and a timetable for its implementation shall be submitted to and approved in writing by the Local Planning Authority. The cycle hire scheme shall be implemented in ... |
NSA |
Prior to construction of the electric vehicle parking spaces as shown on drawing no. 03 Rev I Proposed Block Plan, full details of the spaces and charging points shall be submitted to and approved in writing by the Local Planning Authority. The electric vehicle parking spaces shall be completed in ... |
NSA |
In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing within 2 days to the Local Planning Authority, all associated works must stop, and no further development shall take place unless otherwis... |
NSA |
Any aggregate (other than virgin quarry stone) or recycled aggregate material to be imported shall be assessed for chemical or other potential contaminants in accordance with a scheme of investigation which shall be submitted to and approved in writing by the Local Planning Authority in advance of i... |
LS02 |
All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in the first planting and seeding seasons following the first beneficial use of the development hereby approved; and any trees or plants which within a period of 10 years from the completion of the... |
NONS |
The contamination assessments and the effects of unstable land are considered on the basis of the best information available to the Local Planning Authority and are not necessarily exhaustive. The Authority takes due diligence when assessing these impacts, however you are minded that the responsibil... |
II046 |
New developments of more than one dwelling or where the area covered by construction work equals or exceeds 100 square metres as defined by The Flood and Water Management Act 2010 (Schedule 3), will require SuDS Approval Body (SAB) approval prior to the commencement of construction.
Further info... |
NONS |
Any works to watercourses, including ditches and streams where defined by the Land Drainage Act 1991, require Land Drainage Consent by the relevant drainage body (Lead Local Flood Authority – Vale of Glamorgan Council). Works include any change to the ordinary watercourse that may obstruct or alter ... |
NONS |
In respect of the timing of the erection of the reptile and amphibian barrier as required by condition, it would be expected that such a barrier would be erected in March or April.
|