AAA01 |
The development hereby permitted shall be begun before the expiration of five years from the date of this permission.
Reason:
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990. |
AM01 |
This consent shall relate to the following schedule of plans and documents, and the development shall be carried out strictly in accordance with these details:-
- Site Plan, Location Plan - site edged red location plan, received 21 November 2014;
- Dwg. No. 1421/D01, Demolitions: Site Plan, rece... |
NSA |
Before their use on site a full schedule of external finishes (including samples), for the house, boundary treatment and hard surfacing of on-site car parking and turning facilities, shall be submitted to and agreed in writing with the Local Planning Authority. The development shall be implemented t... |
NSA |
Notwithstanding the submitted plans no works to alter the existing or provide additional entrances to the site from the highway shall commence until further details of the proposed new access and alterations to the existing access, and their associated vehicular crossovers, along with full details o... |
NSA |
Notwithstanding the submitted plans before its implementation on site further details of the proposed projecting canopy, bin and bicycle store on the front, west elevation of the dwelling shall be submitted to and approved in writing with the Local Planning Authority. The development shall be implem... |
NSA |
The proposed on-site car parking/turning areas for the dwelling hereby permitted, as indicated on Dwg. No. 1421/S04A, Ground Floor Plan, amended plan received 22 January 2015, shall be fully implemented before the first beneficial occupation of the dwelling. The parking/turning areas shall thereafte... |
NSA |
Before the commencement of development, including demolition works, the proposed tree protection measures, as indicated in the Tree Survey report dated 3 November 2014, prepared by Treescene, shall be fully implemented and maintained on site for the duration of the demolition and construction works.... |
NSA |
Notwithstanding the submitted plans before the first beneficial occupation of the dwelling hereby permitted further details of the proposed landscaping of the site shall be submitted to and agreed in writing with the Local Planning Authority. The proposed landscaping scheme shall include provision f... |
PD09 |
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (Amendment) (Wales) Order 2013 (or any Order revoking or re-enacting that Order with or without modification) the dwelling hereby approved shall not be extended or altered in any way without the prior wri... |
PD12 |
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (Amendment) (Wales) Order 2013 (or any Order revoking and re-enacting that Order) no building, structure or enclosure required for a purpose incidental to the enjoyment of a dwelling-house shall be constr... |
PD14 |
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (Amendment) (Wales) Order 2013, or any Order revoking or re-enacting that Order, no extension of the roof terrace, as indicated on Dwg. No. 1421/S06A, and no windows other than those expressly authorised ... |
AA122 |
Before the commencement of works on the new dwelling hereby permitted further details of the finished floor levels of the dwelling in relation to existing ground levels and finished ground levels shall be submitted to and approved in writing by the Local Planning Authority and the development shall ... |
AA104 |
The implemented drainage scheme for the site should ensure that all foul and surface water discharges separately from the site and that surface and land drainage run-off shall not discharge, either directly or indirectly, into the public sewerage system.
Reason:
To prevent hydraulic overloadi... |
NSA |
Prior to the commencement of any works on site an appropriately qualified Ecologist shall be utilised to give a ‘toolbox talk’ to contractors carrying out the demolition works and the Ecologist shall directly oversee the stripping of the roof, in particular the roof tiles above the bay window/below ... |
NSA |
The proposed demolition works shall be undertaken outside the bird breeding season, which is generally recognised to be from March to August inclusive, unless a method statement for works is submitted to and agreed in writing with the Local Planning Authority and such agreed method statement shall b... |
II001 |
Where the proposal requires both Planning Permission and Listed Building Consent or Conservation Area Consent work must not be commenced until both consents have been obtained. |
II018 |
Please note that this site lies within a Conservation Area, and as such, any additional works to trees not agreed by this permission will require formal notification. Under the Town and Country Planning Act 1990 a person who wishes to carry out work to trees must give the Local Planning Authority s... |
II021 |
Where the work involves the creation of, or alteration to, an access to a highway the applicant must ensure that all works comply with the appropriate standards of the Council as Highway Authority. For details of the relevant standards contact the Visible Services Division, The Vale of Glamorgan Co... |
II037 |
Should any species listed under Schedules 2 or 5 of the Conservation of Habitats and Species Regulations 2010 subsequently be found to be present on the site in respect of which this permission is hereby granted, you are advised to cease works immediately and contact Natural Resources Wales (NRW), T... |
II040 |
Dwr Cymru Welsh Water (DCWW) have advised that some public sewers and lateral drains may not be recorded on their maps of public sewers because they were originally privately owned and were transferred into public ownership by nature of the Water Industry (Schemes for Adoption of Private Sewers) Reg... |
NONS |
The developer is advised to follow the Vale of Glamorgan Council's Advisory Notes for Demolition and Construction Sites which can be obtained from the Pollution Control team, Tel. 01446 709105 or email: regserv@valeofglamorgan.gov.uk. |